SigenStor Home installation : the complete documentation

SIGENERGY off grid system

« Here is everything you need to know to install a SigenStor Home system properly, from site preparation to commissioning through the mySigen app. This page walks you step by step through the installation of the 5-in-1 SigenStor platform: battery packs, inverter, EV charging module and Sigen LoadHub. Whether you are a certified installer or an informed owner, it is meant as a complete resource for a reliable, code-compliant and optimized installation. »

— Julien, Perma Batteries
📱
Commissioning

The SigenStor Home system is commissioned exclusively through the mySigen app (Android 6.0+ / iOS 12+), after registering an installer account on the Sigen Cloud. An internet connection at the site, by Ethernet, 2.4 GHz WLAN or the 4G Sigen CommMod, is therefore mandatory.

⚠️
Code compliance

SigenStor Home is certified UL 9540 and UL 9540A. The installation must comply with NEC Articles 250, 705, 706 and 710, use the built-in Rapid Shutdown Device (RSD), and be permitted and inspected by the local Authority Having Jurisdiction (AHJ). Only trained, licensed electrical personnel may install the equipment.

🌐
Warranty

To benefit from the manufacturer warranty, SigenStor systems must remain connected to the internet (Sigen Cloud). Ethernet (RJ45) is the most stable option; WLAN and 4G are supported. When the free 4G data of the CommMod runs out, a local SIM card with at least 50 MB/month per inverter must be installed.

SigenStor Home installation: models and system overview

The US version of the SigenStor platform is the SigenStor Home, a split-phase system (240/120 V or 208/120 V AC) built around the SigenStor EC SP US hybrid inverter (Sigen Energy Controller) and stackable SigenStor BAT 6.0 US (6.02 kWh) and SigenStor BAT 9.0 US (9.04 kWh) battery packs. The model name SigenStor-A-B encodes the rated AC power (A) and the battery energy (B).

Seven power ratings are available, from 3.8 kW to 11.5 kW. The rated power of the complete system must match that of the inverter, and the maximum continuous current printed on the inverter nameplate determines the breaker and the AC cable size (see the LoadHub section).

Model (A)Rated AC powerMax. continuous currentAC breaker rating
3.83.8 kW16 A20 A
4.84.8 kW20 A25 A
5.75.7 kW24 A30 A
7.67.6 kW32 A40 A
9.69.6 kW40 A50 A
11.411.4 kW47.5 A60 A
11.511.5 kW48 A60 A

AC input/output power at 240/120 V or 208/120 V AC. AC switch rated voltage ≥ 240 V AC. Source: SigenStor Home Installation Guide (US) v08.

Battery energy (B) is obtained by stacking up to six packs per inverter, mixing 6.0 and 9.0 packs freely. The table below lists every supported configuration, from a single 6 kWh pack to 54 kWh per stack.

Battery energy (kWh)BAT 6.0 USBAT 9.0 USBattery energy (kWh)BAT 6.0 USBAT 9.0 US
6.021030.1222
9.040133.1413
12.042036.1604
15.061139.1623
18.080242.1814
21.082145.2005
24.101248.2024
27.120351.2215
54.2406

Up to six SigenStor BAT for floor installation, up to two for wall installation. Several inverters can be paralleled behind a Sigen LoadHub.

A complete system is made of the following components: PV modules (A), the SigenStor EC inverter (B), one or more SigenStor BAT (C), an AC switch per inverter (D), the Sigen LoadHub (E, mandatory for any backup wiring), backup and non-backup home loads (F1/F2) and electric panels (G1/G2), an optional generator (H), smart loads (I) such as heat pumps, pool heaters or clothes dryers that can be shed when storage is low, a power sensor (J: Sigen Sensor SP CT250 US or CT200-DH US) or an external CT (K: CT-EC) for zero-export control, the grid (L), the mySigen app (M), a router (N), the WLAN antenna (O) and the Sigen CommMod US for 4G (P).

✅
Key point

Sigen LoadHub replaces the European Gateway: it is a must-have for any backup wiring, generator control and off-grid operation. A sensor-only installation (no LoadHub) gives self-consumption and zero-export, but no backup.

Inverter connectors: port description

The connection area of the SigenStor EC SP US is located on the left side of the inverter, behind the junction box cover. The US inverter differs from the European SP range on two points: the AC terminal block is split-phase (L1 / N / L2), and a Rapid Shutdown Device (RSD) with its initiator replaces the DC switch.

#MarkingName and function
1–RSD Initiator (rapid shutdown trigger switch)
2LEDDecorative cover light strip connector
3RJ45 1 / RJ45 2Network interfaces: one to the router, one to other equipment (inverter, Sigen LoadHub)
4RSDRapid Shutdown Device
5L1 / N / L2AC terminal block (split-phase)
6–Ground screw
7–Grounding aluminum busbar
8PV1± to PV4±DC terminal block, four PV string inputs
9–Signal terminal block (RS485, CT, EPO, backup switch, DO/DI)
10ANTWLAN antenna port
114GSigen CommMod port
12ON/OFFOn-Off switch

Port numbering as in the SigenStor Home Installation Guide (US), section 1.4.

⚡
Power-off before any work

Before connecting cables, the RSD trigger switch must be OFF and the upstream AC breaker open. Never work on the equipment with power on: disconnect grid, inverter and generator switches, connect the ground cable first and remove it last.

Sigen LoadHub: wiring, breakers and cable sizes

⚠️
Mandatory

The Sigen LoadHub is mandatory for whole-home or partial backup, for generator control and for off-grid use. Its detailed wiring is covered in the separate Sigenergy LoadHub Installation Guide.

1. Which cable size between the inverter and the LoadHub or panel?

The AC cable is an outdoor four-core copper cable (L1, L2, N, PE), rated 90 °C or 105 °C, outer diameter 0.2–0.35 in (5–9 mm), stripped 0.39–0.47 in (10–12 mm). L1, L2, N and PE must be connected to the other equipment in sequence, without mixing. The conductor size depends on the maximum continuous current checked on the inverter nameplate:

Nameplate max. continuous currentMinimum AC conductorUpstream breaker
16 A12 AWG (3 mm²)20 A
20 A10 AWG (5 mm²)25 A
24 A10 AWG (5 mm²)30 A
32 A8 AWG (8 mm²)40 A
40 A8 AWG (8 mm²)50 A
47.5 / 48 A6 AWG (13 mm²)60 A

Installer-provided cables must comply with national and local codes (NEC). Undersized conductors do not guarantee the safety of people and property.

2. Which cable sizes for signal, network and DC?

CableTypeConductorOuter diameterLimits
SignalOutdoor shielded twisted pair20–18 AWG (0.5–0.75 mm²)0.18–0.25 in (4.5–6.5 mm)≤ 3,280 ft (1,000 m), ≤ 9,600 bps
NetworkOutdoor 8-conductor shielded twisted pair, EIA/TIA 568B26–24 AWG (0.13–0.20 mm²)0.16–0.30 in (4–7.5 mm)≤ 328 ft (100 m) per cable
DC (PV)Outdoor photovoltaic cable, 90 °C11–9 AWG (4–6 mm²)0.18–0.31 in (4.5–7.8 mm)Stripped 10–12 mm

When conduit is used, the recommended pipe diameter is at least 1 in (25.4 mm) or 1-1/4 in (31.75 mm). Cables are routed through the junction box side hole; elbows are installer-supplied and must be waterproofed.

3. Sizing the backup panel breaker

The AC switch of the distribution panel must be rated at least 240 V AC, with a current rating of not less than the maximum output current of one inverter × the number of inverters in parallel × 1.25. The maximum output current is given in the inverter datasheet.

4. The LoadHub, wiring principle

The Sigen LoadHub sits between the utility service and the home. In a backup wiring, the backup panel (G1) feeding the backup loads (F1) is connected downstream of the LoadHub, while the non-backup panel (G2) and its loads (F2) remain on the grid side. Each inverter connects to the LoadHub through its own AC switch (D), and the generator (H) connects to the dedicated LoadHub input.

The service ground bond must be connected to the grounding terminal located in the Sigen LoadHub or in the residential service panel, and the system must have only one ground bond connection, in accordance with NEC Article 250. In a whole-home backup wiring, no power sensor or CT is required: all energy is metered through the LoadHub.

✅
Advantage: whole-home backup

With the LoadHub, the complete home panel can be backed up by the SigenStor battery. High-power equipment (heat pumps, pool heaters, dryers) should be wired as smart loads so it can be shed automatically when storage runs low.

Site requirements and mounting of inverter and battery packs

1. Installation environment

Install the equipment in a sheltered place, away from direct sunlight, rain, standing water, snow and dust, and never in a smoky, flammable or explosive environment or one with strong electromagnetic interference. The operating range is −4 °F to 131 °F (−20 to 55 °C) and 5–95 % RH. Keep at least 1,640 ft (500 m) from corrosion sources (seaside, chemical or coal plants, electroplating), relaxed to 656 ft (200 m) in mild marine environments such as California (≤ 28 psu).

The equipment must be installed horizontally, out of reach of children, away from fire hazards and moisture, in a ventilated, non-sealed location accessible to firefighters, with a minimum room volume of 267 ft³ (7.57 m³). Indoors, keep the temperature rise below 5.4 °F (3 °C) during operation, or the system will derate. It makes some noise when operating. Mobile installations (RVs, boats, trains) are prohibited, and in a garage the unit must stay out of the vehicle path. The system is flood resistant up to 1.97 in (50 mm).

2. Mounting surface and clearances

Do not install on a flammable base. Solid brick-concrete, wooden walls, concrete walls and floors are recommended; the base must be flat, load-bearing, and free of plumbing or electrical runs behind the drilling points. The aluminum base requires insulating gaskets (PC, PTFE or PVDF) when mounted on a metallic substrate prone to electrochemical corrosion.

Recommended clearances: ≥ 15.75 in (400 mm) above, ≥ 11.81 in (300 mm) on each side, ≥ 13.78 in (350 mm) to the ground reference, ≥ 19.69 in (500 mm) front to front between facing units, and ≥ 6.3 in (160 mm) back to back with a baffle plate. Tilt must not exceed 5° sideways or 2° front to back. Keep heat sources at a distance.

3. Floor and wall installation

Floor installation supports up to six SigenStor BAT; use the lift for three or more packs. If the floor is prone to stagnant water, build a waterproofing platform or wall-mount. When a floor mounting pad is used, it must be at least 2 in (51 mm) thick and 16 × 36 in (406 × 914 mm), with the equipment centered and no settlement or water accumulation. Stacks of up to four layers may be wall- or floor-mounted; above four layers, wall and floor mounting must be combined.

BAT unitsPad bearing capacity (BAT + EC)Pad bearing capacity (BAT + EC + EV DC module)L, controller bracket to ground
1317 lb (144 kg)430 lb (195 kg)22.60–22.87 in (574–581 mm)
2520 lb (236 kg)633 lb (287 kg)33.23–33.50 in (844–851 mm)
3723 lb (328 kg)836 lb (379 kg)43.86–44.13 in (1114–1121 mm)
4927 lb (420 kg)1,040 lb (472 kg)54.49–54.76 in (1384–1391 mm)
51,130 lb (513 kg)1,243 lb (564 kg)65.12–65.39 in (1654–1661 mm)
61,333 lb (604 kg)–75.75–76.02 in (1924–1931 mm)

Wall installation: up to two BAT; L from controller bracket to base wall-mount bracket = 23.70–23.94 in (602–608 mm) for one pack, 34.33–34.57 in (872–878 mm) for two.

Before fitting the handle, check with a torque wrench that the screws on each SigenStor BAT are tightened to 4.5 N·m (±0.45). Use the new handle supplied with the inverter, « OUT » lettering facing outwards; a handle with damaged or missing stoppers must not be used, and a handle is scrapped after 100 uses. The handle and all accessories are the owner’s property and stay on site. Battery packs are kept horizontal and lowered vertically; wrap the sling contact areas during lifting. A pack that has been dropped or shocked must not be used: buy a new one. Optionally, the right-side inverter padlock (bar diameter ≤ 0.20 in / 5 mm) deters theft.

📋
Site checklist

Sheltered, ventilated, non-flammable base · ≥ 267 ft³ room · clearances 400 / 300 / 350 mm · tilt ≤ 5° / 2° · 500 m from corrosion sources · lift for ≥ 3 packs · wall + floor above 4 layers · 4.5 N·m on BAT screws.

Wiring configurations: backup, non-backup, retrofit

1. Grid-tied installation without backup (no LoadHub)

For a SigenStor installation without backup, you only need a grid metering device at the service entrance: either a Sigen Sensor power meter (SP CT250 US / DTSU666 or SP CT200-DH US / SDM630MCT ETL, on RS485) or the external CT-EC on the signal terminal. Either one enables zero-export (zero-power) grid connection; never connect both at the same time. Each inverter is protected by its own AC switch in the panel.

2. Installation with whole-home backup (Sigen LoadHub)

For whole-home backup in case of a grid outage, the Sigen LoadHub is integrated between the service and the panels. No Sigen Sensor is then needed, since all energy flows are metered inside the LoadHub. The LoadHub also handles off-grid switching and generator control. A partial backup is possible with a backup panel (G1) and a non-backup panel (G2); zero-export control in a partial backup wiring still requires a power sensor.

3. I already have a solar inverter: can it be integrated?

If you already own a PV system with microinverters (Enphase, Hoymiles, etc.) or a string inverter (SMA, Fronius, etc.), you are in a retrofit scenario: the existing production is re-integrated into the SigenStor system so that surplus solar automatically recharges the batteries. The third-party inverter output is measured by a CT wired to the IC+ / IC− terminals (pins 10 / 8) of the signal block. See section 9.

✅
Which configuration?

No backup needed: inverter + Sigen Sensor or CT. Backup, off-grid or generator: add the Sigen LoadHub. Existing PV: keep it, add a CT on the third-party inverter output.

Connecting a generator to the Sigen LoadHub

For an isolated site or long outages, a generator can be used as a backup energy source for long-term off-grid operation. It connects to the dedicated input of the Sigen LoadHub, which provides a smooth transition between PV, storage and generation, and can start the generator automatically when the batteries reach a set state-of-charge threshold, configured in the mySigen app.

⚠️
Mandatory

A Sigen LoadHub is required to use a generator. The generator must never be connected directly to the inverter AC terminals, and its power switch must be off during any wiring work.

Powering on and commissioning with the mySigen app

1. Post-installation check

Before power-on, verify that: the equipment is securely installed; ground, DC and signal cables are correctly installed with no leftovers; cable ties have no sharp cut points; the RSD trigger switch is OFF; unused ports have their waterproof covers or plugs; and no construction debris remains inside or outside the equipment. Then install the junction box protective cover and the SigenStor BAT and Energy Controller decorative covers (the strip-light end plug at the lower left of the inverter is removed and kept as a spare; if the strip light misbehaves at power-on, check for a tilted pin in the male connector and re-seat the connectors).

2. Power-on sequence

1. Turn on the upstream switch of the equipment. 2. Rotate the RSD trigger switch to ON. 3. Observe the indicators on the front of the inverter (see section 12). 4. After power-on, install the remaining decorative covers.

3. Creating the system in mySigen

1. Register an installer account on the Sigen Cloud business portal. 2. Download the mySigen app (Android 6.0+, iOS 12+) and create a new system: scan the SN label on the packing box, or on the side of the inverter if the label is lost, and follow the on-screen prompts or the « mySigen App Creating New Systems Guide ». 3. Ask the owner to check the e-mail titled « sigencloud » and activate the account within 24 hours after the system is created. The 5-in-1 modules (battery, inverter, EV charger, LoadHub) are then configured and monitored in real time from the app.

✅
Commissioning in short

Post-installation check → covers → upstream switch ON → RSD ON → LEDs → mySigen: scan SN, create system, owner activates the sigencloud e-mail within 24 h.

Adding a new battery pack to the installation

SigenStor BAT packs are added by stacking, without cabling, up to six packs per inverter on the floor (two on the wall). Sigenergy asks installers to consult the owner about expansion requirements before the initial installation (additional battery packs, Sigen EV DC Charging Module) and to reserve the corresponding space and cable length.

When adding a pack later: power off the system (upstream switch and RSD OFF) and wait the delay stated on the equipment label; remove the decorative covers and the inverter; lower the new pack vertically onto the stack with the handle (lift required from three packs); check the 4.5 N·m screw torque; add the cascaded plate and, above four layers, the wall fastener; refit the inverter and covers; power on and let mySigen detect the new pack. Only Sigenergy battery packs may be used: mixing other brands voids the warranty. A new 6.0 or 9.0 pack can be combined with the existing ones in any of the configurations listed in section 1.

💡
Key point

Plan the expansion at the first installation: space above the stack, pad bearing capacity, and whether a fifth or sixth pack will require combined wall and floor mounting.

Integrating a solar inverter already installed

Procedure when the owner already has a standard solar inverter (Enphase, SMA, Fronius, etc.). Its integration in the SigenStor system lets the app track the existing solar production and use the surplus to recharge the SigenStor batteries. During a grid outage (off-grid operation behind the LoadHub), third-party inverters can be controlled by the Sigen system.

Wiring: a CT on the output of the third-party inverter is connected to the IC− (pin 8) and IC+ (pin 10) terminals of the signal block. The grid connection point is measured either by the external CT (IA/IB) or by a Sigen Sensor on RS485. The DO+ / DO− digital output (pins 9 / 11, 12 V, 1 A max) can drive third-party smart equipment such as switch controllers or heat pumps.

✅
Advantage: open platform

Existing PV is kept and metered, surplus charges the battery, and smart loads can be driven through the digital output: no need to scrap a working solar array.

Wiring the Sigen Sensor and CT on the signal terminal

The CT sensor and the power sensor have the same function; only one of them may be connected, and both must be purchased from Sigenergy’s official channels. The CT cable is 19.69 ft (6 m). The power sensor is wired on RS485 with an outdoor shielded twisted pair (20–18 AWG), stripped 0.79–1 in (20–25 mm) on the sheath and 0.43–0.47 in (11–12 mm) on the conductors, shield grounded.

Two markings of the signal terminal exist: on Marking 1, pin 2 is PE (shield ground); on Marking 2, pin 2 is GND and pins 9 / 11 become the DO+ / DO− digital output. Refer to the marking on the device you received.

PinMarkingFunction
1485−RS485 signal B− (power sensor): CT250 US terminal B / CT200-DH US terminal 13
3485+RS485 signal A+ (power sensor): CT250 US terminal A / CT200-DH US terminal 14
2PE or GNDShield ground (Marking 1) or digital GND (Marking 2)
4 / 6IA− / IA+External CT, L1 grid connection point
5 / 7IB− / IB+External CT, L2 grid connection point
8 / 10IC− / IC+CT on third-party inverter output (retrofit)
9 / 11DO+ / DO−Digital output, 12 V / 1 A, smart loads (Marking 2); reserved on Marking 1
12MC+12 V+ supply for Sigen Backup switch
13GNDCommon point for digital inputs
14DI1Digital input 1 (reserved)
15 / 16EPO+ / EPO−Emergency Power Off button, factory short-circuited

EPO cable 20–18 AWG (0.5–0.8 mm²), switch fitted with a protective cover, cable in a protective tube. Network cables: two RJ45 ports, one to the router, one to other equipment.

⚠️
One sensor only

Never connect the CT-EC and a Sigen Sensor together. For a whole-home backup behind the LoadHub, neither is needed.

Certifications and code compliance (UL, NEC, CEC)

SigenStor Home complies with UL 9540:2025 (report No. 80172701) and UL 9540A:2025 (report No. 80263447 unit level, No. 80263446 module level), certified by CSA Group Testing & Certification Inc. These reports are the documents to provide with the permit application to the AHJ.

Installation requirements in the United States: single ground bond connection per NEC Article 250; directory plaques on all service equipment identifying every power source per NEC Articles 705, 706 and 710; rapid shutdown. When off-grid is disabled, the Energy Controller detects grid faults from voltage and frequency per the grid code and switches to anti-islanding mode within 2 seconds, disconnecting the DER relay. The AC output short-circuit rating of the output breaker must be at least 313.04 A rms for 162 ms.

Canada (CEC Rule 64-1100): thanks to its UL 9540A unit-level results, the system is authorized beyond the usual residential limits, up to 54 kWh per stack and 216 kWh per system in non-habitable residential space, with a minimum room volume of 267 ft³. The installer must apply a permanent marking on the enclosure stating the UL 9540A report number (80263447) and the actual installed capacity in kWh, and follow CEC Section 64 location requirements.

📋
Documents for the permit

UL 9540 and UL 9540A reports, inverter datasheet (max. output current), single-line diagram with LoadHub, directory plaques, and in Canada the field marking with report number and installed kWh.

Meaning of the LED indicators on the inverter

The front of the SigenStor EC carries five indicators: DC (PV side), AC, energy storage, DC charger and signal. Their color and state give the system status at a glance.

IndicatorColorStateMeaning
DCWhiteAlways onDC side connected but not running
DCGreenAlways onDC side running
DCGreyOffDC side not connected
DCOrangeFlashingDC side faulty
DCRedAlways onInverter faulty
ACWhiteAlways onAC side connected but not running
ACGreenAlways onGrid-connected operation
ACBlueAlways onOff-grid operation
ACGreyOffAC side not connected
ACBlueFlashingOff-grid overload
ACOrangeFlashingAC side faulty
ACRedAlways onInverter faulty
Energy storageWhiteAlways onAll BATs connected, not running
Energy storageGreenFlashingBAT charging
Energy storageBlueFlashingBAT discharging
Energy storageGreyOffAll BATs dormant
Energy storageOrangeFlashingSome BATs faulty
Energy storageRedAlways onAll BATs faulty
SignalGreyOffManagement system not connected
SignalGreenFlashingConnected to local app
SignalGreenAlways onConnected to cloud by Ethernet or WLAN
SignalBlueAlways onConnected to cloud over 4G
SignalBlueFlashingInsufficient 4G data on Sigen CommMod

Sigen CommMod network indicator: slow flash 200 ms on / 1800 ms off = connecting; 1800 ms on / 200 ms off = standby; quick flash 125 ms = data transfer.

Maintenance, storage and handling requirements

The SigenStor range is designed for durable performance with minimal maintenance. To guarantee safety, efficiency and longevity of the battery packs, hybrid inverter, EV charging module and LoadHub, follow these rules from the Sigenergy Important Notice.

1. Routine maintenance

Inspect the enclosure and repair paint scratches promptly: rust caused by unrepaired paint is not covered by the warranty. Keep the equipment clean without water, alcohol or oil, check cable connections and ventilation, and keep the firmware up to date through the OTA updates in the mySigen app. Before any maintenance or replacement, power off and wait the delay stated on the equipment label; power on only after the fault is fully rectified.

2. Battery pack replacement

Battery energy storage systems carry a fire risk, and faulty packs may release flammable and toxic gases: replacement is performed or supervised by trained professionals only. Use Sigenergy packs only, never mix brands. A faulty pack may be hot: do not touch it bare-handed, store it away from flammable environments and non-professionals, and monitor it for leakage, heat or flame.

3. Storage of battery packs

Store packs unopened, apart from other items, with fire extinguishers on site, protected from sunlight, moisture, insects and rodents. Storage temperature −25 to 60 °C (20–30 °C recommended), 5–95 % RH. Packs are stored at 40 % ± 5 % SOC; inventory is counted monthly and packs recharged before the period below expires, following first-in, first-out. After 12 months at the recommended temperature the irreversible capacity loss is 3 to 10 %; packs stored beyond the period must be tested by qualified personnel.

Actual storage temperatureRecharge period
T ≤ −25 °CNot allowed
−25 °C < T ≤ 25 °C15 months
25 °C < T ≤ 35 °C9 months
35 °C < T ≤ 60 °C6 months
T > 60 °CNot allowed

Storage time counts from the shipping date on the outer packaging; update the last charging date after each recharge.

4. Handling and transportation

SigenStor BAT is Class 9 dangerous goods (UN38.3). Wear PPE, follow the package orientation marking, never tilt beyond 15° packed or 10° unpacked, and use a forklift with the forks centered. Transport by rail and air is prohibited; sea transport follows the IMDG Code and road transport the applicable dangerous goods regulations. Keep ≥ 0.8 m from food, medicine or feed, never with flammable or corrosive goods. A pack that has been dropped, shocked or submerged must not be used, and one exposed to rain or snow must be evaluated by a professional first. Cables must be installed above 0 °C (acclimatize 24 h if stored colder).

✅
Maintenance in short

Visual check and paint touch-up · connections and ventilation · OTA updates in mySigen · spare packs at 40 % SOC, recharged every 6 to 15 months depending on temperature · Sigenergy packs only.

Official documentation and quotes

Download the SigenStor Home Installation Guide (US) and the Important Notice, or browse the full Sigenergy documentation center. For a sized system, a LoadHub or a Sigen Sensor, contact Perma Batteries.

📞 +1 (415) 818-0845✉️ inquiries-usa@perma-batteries.com🔋 Sigenergy certified partner

Powered By EmbedPress

SigenStor Home US summary table

Key installation data at a glance

ItemValue
InverterSigenStor EC SP US, split-phase 240/120 V or 208/120 V AC, 3.8 to 11.5 kW
Battery packsSigenStor BAT 6.0 US (6.02 kWh) and 9.0 US (9.04 kWh), mixable
Packs per stackUp to 6 on the floor, 2 on the wall, 54.24 kWh max per stack
Max. system capacity (Canada, CEC 64-1100)216 kWh, min. room volume 267 ft³ (7.57 m³)
PV inputs4 strings (PV1 to PV4), DC cable 11–9 AWG
AC cable4-core copper L1/L2/N/PE, 12 to 6 AWG by nameplate current, 90/105 °C
AC breaker per inverter20 / 25 / 30 / 40 / 50 / 60 A for 16 / 20 / 24 / 32 / 40 / 47.5–48 A
Backup panel breaker≥ max. output current × inverters in parallel × 1.25
Backup / generator / off-gridSigen LoadHub mandatory
Grid metering (no LoadHub)Sigen Sensor SP CT250 US or CT200-DH US (RS485) or CT-EC, never both
Operating range−4 to 131 °F (−20 to 55 °C), 5–95 % RH
Clearances≥ 400 mm above, 300 mm sides, 350 mm to ground, 500 mm front-to-front
Tilt tolerance≤ 5° sideways, ≤ 2° front to back
Flood resistanceUp to 1.97 in (50 mm)
BAT screw torque4.5 N·m ± 0.45
CommunicationEthernet (2 × RJ45), WLAN 2.4 GHz, 4G Sigen CommMod US (≥ 50 MB/month per inverter)
AppmySigen, Android 6.0+ / iOS 12+, account activation within 24 h
CertificationsUL 9540:2025, UL 9540A:2025 (unit and module level), CSA Group
CodesNEC 250, 705, 706, 710; CEC Section 64 (Canada)
Anti-islandingWithin 2 s after grid-code clearing time
Spare pack storage40 ± 5 % SOC, recharge every 15 / 9 / 6 months by temperature

Data from the SigenStor Home Installation Guide (US) v08 (2026-09-21) and the SigenStor Home Important Notice v04. Always check the latest revision on the Sigenergy documentation center.

FAQ: your questions on SigenStor installation

Do I need the Sigen LoadHub?

Yes for any backup (whole-home or partial), for off-grid operation and to connect a generator. For a grid-tied system with self-consumption only, a Sigen Sensor or an external CT at the service entrance is enough.

Which breaker and cable for my inverter?

It depends on the maximum continuous current printed on the nameplate: 16 A needs a 20 A breaker and 12 AWG, 20 and 24 A a 25 or 30 A breaker and 10 AWG, 32 and 40 A a 40 or 50 A breaker and 8 AWG, 47.5 or 48 A a 60 A breaker and 6 AWG. The backup panel breaker is sized at the maximum output current times the number of inverters times 1.25.

How many battery packs can I stack?

Up to six SigenStor BAT per inverter on the floor, mixing 6.0 and 9.0 packs, for 54 kWh per stack. Wall mounting is limited to two packs, and above four layers both wall and floor mounting must be used together. A lift is required from three packs.

Can I connect both a CT and a Sigen Sensor?

No. The CT sensor and the power sensor have the same function and only one may be connected. Behind a LoadHub in whole-home backup, neither is required.

How is the system commissioned?

Only through the mySigen app: register an installer account on the Sigen Cloud, create the system by scanning the inverter SN, and have the owner activate the sigencloud e-mail within 24 hours. Before that, complete the post-installation check, close the upstream switch and turn the RSD switch ON.

What certifications does SigenStor Home carry for the permit?

UL 9540:2025 and UL 9540A:2025 unit and module level, certified by CSA Group. The installation must follow NEC Articles 250, 705, 706 and 710, and in Canada CEC Rule 64-1100 and Section 64, with a field marking of the UL 9540A report number and installed kWh.

How long can a spare battery pack be stored?

At 40 % SOC: 15 months below 25 degrees C, 9 months up to 35 degrees C, 6 months up to 60 degrees C, counted from the shipping date. Beyond that the pack must be tested by qualified personnel.